FINAL TESTING & FACTORY ACCEPTANCE TEST

Let the system pass with complete evidence
in final factory acceptance

On the freeze configuration, pre-sequencing tests, system-level validation, failure response, witness records and delivery evidence are consolidated into the same FAT acceptance system. FAT does not repeat all of the tests, but completes the final confirmation that can be witnessed, audited, released on the final scope baseline.

The final conclusion can only be an official technical authorization to enter the PSI if it is based on a complete chain of evidence.
IF APPLICABLE
NOT ASSUMED
Third party/client witness
Witness record.

01 Configuration Freezing and Receiving and Inspection Files

Design baseline Approved Design Baseline
BOM and physical consistency BOM / As-built
Version baseline HW R03 / SBMS R05 / EMS R08 / PCS R04
Configuration Status
CONFIGURATION
FROZEN ✓
Approval for deviation Approved Deviations
Instrument validity Calibration Validity · 100%
Precondition release Prerequisite Releases · 12 / 12 ACCEPTED
Witness. Witness Plan

02 General FAT Test Range

Electrical security Electrical Safety · 8 cases
Protection and failure response Protection / Fault · 12 cases
Function Logic Functional Logic · 6 cases
FAT
Test Range 48 TEST CASES
Run Controlled Controlled Operation · 10 cases
Communications Communication · 6 cases
Cool and alarm/ fire interface Cooling & Alarm / Fire · 6 cases
Electrical security: Eight examples of electrical safety tests for polarity, PE continuity, insulation, resistance, prefilling and safe discharge.
01 Safety first Safety Ready
02 Controlled Run Controlled Operation
03 Functional Logic Functional Logic
04 Communications Communication
05 Interface Validation Interfaces
06 Fault and release Fault / Conclusion

03 Electrical security doors

Test Project Test Example ID Status Wave / Data
Polarization / Polity TC-DEMO-FATR-ES-0001 PASS
Protection of continuity / PE Continuity TC-DEMO-FATR-ES-0002 PASS
Insulation resistance TC-DEMO-FATR-ES-0003 PASS
Insulation / Dielectric Withstand TC-DEMO-FATR-ES-0004 PASS
Insulation monitoring / Isolation Monitor TC-DEMO-FATR-ES-0005 PASS
Prefill / Pre-Charge TC-DEMO-FATR-ES-0006 PASS
Emergency isolation TC-DEMO-FATR-ES-0007 PASS
Safe discharge / Safe Discharge TC-DEMO-FATR-ES-0008 PASS

04 Controlled running door

Start / Stop PASS
Power Command Range ±1.25 MW
SOC Window 20% – 90%
Cool the response. PASS
Communications and status PASS

05 Security and malfunction doors

scene Expected action Interface / Record Status Result
Suspended button E-Stop Stop now and stop power output. Match No duplicates
The doorlock. Ban startup, alert. Match The strategy is right.
High temperature alert. Decline / Stop / Alert Match Autorecover
Interrupted communication EMS↔PCS Keep your power safe. Match Log Complete
BMS failure. System Segregation / Disable Output Match Block Establishment
Internal PCS failure Stop and report. Match Unrecovered
Fire safety trigger. Implementation of fire-fighting strategy Match Steady.
Insulation surveillance anomaly Stop and report. Match Correct.

06 Witness observation closed to Punch List

Observation item: HMI bilingual warning description does not match the text of the live warning board
FAT OBS TC-DEMO-FAT-OBS-0012 · OPEN / TEST GROUP HELD
Original alarm. Chinese: Battery high temperature alert English: Battery High Temp Alarm
That's right. Chinese: Battery temperature alarms English: Battery Temperature High Alarm
Textual amendments DICT R12 → R13
Interface Retrometry PASS
Problem Close CLOSED
Test Record Date/ Time Result Witness
TC-DEMO-FATR-OBS-0012-RT01 2025-05-30 14:22 PASS / Project
Observation status at FAT test: Cristical 0. Major 0. Minor 0. Documentation 0
0 OPEN

07 Final status of 48 cases

First adopted 47
Adopted as amended 1
Total 48 / 48
Issues of openness 0
Category Examples used First adopted Adopted as amended Final pass rate
Electrical security 8 8 0 100%
Run Controlled 10 10 0 100%
Protection and failure 12 11 1 100%
Communications 6 6 0 100%
Function Logic 6 6 0 100%
Cool and alarm/ fire interface 6 6 0 100%
Total 48 47 1 100%

08 Multi-role approval of workflow

Phase Role Duties Approval time Certificate Record Hash.
1 Production review Complete physical and manufacturing records 2025-05-21 09:18 Production SHA256 5F7A...B82E
2 Quality review Conformity and completeness of evidence 2025-05-21 11:42 Quality SHA256 7CD0...2A91
3 Project approval Technical release and risk identification 2025-05-21 14:27 Engineering SHA256 A4E9...7D3C
4 Client/ Third Party Witness Witness confirmation (if applicable) IF APPLICABLE — —
(a) FAT technology release requires at least the completion of production, quality and tripartite approval of the works;

09 FAT evidence bag

FAT EVIDENCE
PACKAGE
FAT plan and sequence: Controlled FAT Test Sequence defines the order of execution, pre-conditions, roles and determination of 48 examples.
FAT PASSED → READY FOR PRE-SHIPMENT INSPECTION
✓ FAT technology release 48/48 PASS
PSI PSI Pre-export inspection
PKG Packaging Transfer Packaging Handover
SITE Incoming and accepted Site Acceptance
COM Run Delivery Commissioning
Stage boundary: FAT PASS indicated that the final plant acceptance test was completed and the system was authorized to enter the PSI. It does not represent completion of PSI, packaging, shipment, on-site SAT or Commissioning.

11 Criteria and project basis Context

CON Contract and FAT Regulation Contractual FAT Specification
62933 IEC 62933 Power Energy Storage Systems Safety and System Level Requirements
BAT IEC 62619 / 63056 Safety requirements for industrial and storage lithium batteries
UL UL 9540 / NFPA 855 Security and engineering boundary of Energy Storage Systems
62477 IEC 62477-1 Electrical and electronic transformation equipment security context
INT Internal acceptance guidelines TIANCHU Acceptance Criteria